Procedural Schedule

January 1, 2027

Estimated energization

July 26, 2026

Substation construction estimated to begin

May 21, 2026

Electrical work estimated to begin

May 21, 2026

Mechanical work estimated to begin

April 2, 2026

Civil construction estimated to begin

March 30, 2026

OPSB Preconstruction Meeting

June 8, 2022

12:00 pm Stipulation Due

June 8, 2022

10:00 am Evidentiary Hearing

June 3, 2022

Staff/Intervenor Testimony Due

May 27, 2022

Nottingham Testimony Due

May 24, 2022

List of Issues due

May 17, 2022

6:00 pm Public Hearing - New Athens Volunteer Fire Department. Address: 101 Franklin Dr., New Athens, Ohio 43981

 

May 2, 2022

OPSB Staff Report Due